If you want to choose passing Nokia certification SDM_2002001040 exam to make yourself have a more stable position in today's competitive IT area and the professional ability become more powerful, you must have a strong expertise. And passing Nokia certification SDM_2002001040 exam is not very simple. Perhaps passing Nokia certification SDM_2002001040 exam is a stepping stone to promote yourself in the IT area, but it doesn't need to spend a lot of time and effort to review the relevant knowledge, you can choose to use our IT-Tests.com product, a training tool prepared for the IT certification exams.
IT-Tests.com site has a long history of providing Nokia SDM_2002001050 exam certification training materials. It has been a long time in certified IT industry with well-known position and visibility. Our Nokia SDM_2002001050 exam training materials contains questions and answers. Our experienced team of IT experts through their own knowledge and experience continue to explore the exam information. It contains the real exam questions, if you want to participate in the Nokia SDM_2002001050 examination certification, select IT-Tests.com is unquestionable choice.
In order to pass Nokia certification SDM_2002001050 exam, selecting the appropriate training tools is very necessary. And professional study materials about Nokia certification SDM_2002001050 exam is a very important part. Our IT-Tests can have a good and quick provide of professional study materials about Nokia certification SDM_2002001050 exam. Our IT-Tests.com IT experts are very experienced and their study materials are very close to the actual exam questions, almost the same. IT-Tests.com is a convenient website specifically for people who want to take the certification exams, which can effectively help the candidates to pass the exam.
Exam Name: SDM Certification - CARE
Free One year updates to match real exam scenarios, 100% pass and refund Warranty.
SDM_2002001040 Exam Cost Total Q&A: 121 Questions and Answers
Last Update: 2014-08-16
Exam Name: SDM Certification - NI
Free One year updates to match real exam scenarios, 100% pass and refund Warranty.
SDM_2002001050 Exam Prep Total Q&A: 160 Questions and Answers
Last Update: 2014-08-16
IT-Tests.com is a website that specializes in providing IT exam information. The pass rate can achieve 100%. Which is one of the reasons that most candidates willing to believe the IT-Tests.com. IT-Tests.com have been always concerned about the needs of the majority of candidates. We always with the greatest ability to meet the needs of the candidates . IT-Tests.com's Nokia SDM_2002001040 exam training materials is an unprecedented IT certification training materials. With it, your future career will be rain or shine.
There are too many variables and unknown temptation in life. So we should lay a solid foundation when we are still young. Are you ready? Working in the IT industry, do you feel a sense of urgency? IT-Tests.com's Nokia SDM_2002001040 exam training materials is the best training materials. Select the IT-Tests.com, then you will open your door to success. Come on!
IT-Tests.com is a website that provide the counseling courses for IT professionals to participate in Nokia certification SDM_2002001050 exam and help them get the Nokia SDM_2002001050 certification. The courses of IT-Tests.com is developed by experienced experts' extensive experience and expertise and the quality is very good and have a very fast update rate. Besides, exercises we provide are very close to the real exam questions, almost the same. When you select IT-Tests, you are sure to 100% pass your first time to participate in the difficult and critical Nokia certification SDM_2002001050 exam.
SDM_2002001050 (SDM Certification - NI) Free Demo Download: http://www.it-tests.com/SDM_2002001050.html
NO.1 During the start up phase of a project the PM is preparing the project management plan. Who
should approve the plan and fully commit to the execution of it?
A. The CT Head.
B. The Head of NI Region/Sub region.
C. The Head of GS Region/Sub region.
D. The Head of PMS of the Region/Sub region.
Answer: A
Nokia SDM_2002001050 braindump SDM_2002001050 Braindumps
NO.2 How should integration engineer resources be planned for the RA network integration?
A. Include an estimation of local resources in the project headcount.
B. Prepare an RFQ for external suppliers with the support of Procurement.
C. Include the input from GNIC into your service cost estimation.
D. Communicate the need of integration engineers for your project during the MRM (Monthly
Resource Meeting).
Answer: C
Nokia questions SDM_2002001050 SDM_2002001050 Exam PDF SDM_2002001050 Practice Exam
7. What is RTI?
A. Interface between Site quality module and IPM.
B. Interface between SAP and IPM.
C. An external database linking SAP and E-doc
D. Interface between Change management and Quality module.
Answer: B
Nokia exam prep SDM_2002001050 pdf SDM_2002001050 Practice Exam SDM_2002001050 test
8. When does the PM need to update NELLE with customer/project data?
A. At year end.
B. After the customer forecast is received.
C. Per STP .
D. At least once a month, before period cut-off.
Answer: D
Nokia SDM_2002001050 Exam Cram SDM_2002001050 Dumps PDF SDM_2002001050 Exam Tests
9. As part of the start-up activities the PM is defining a communication plan. What is the content
of such a plan?
A. Share of responsibility, project organisation chart and escalation process.
B. Employee list with phone numbers and e-mail addresses, CT/project organisation and
communication matrix.
C. Communication matrix, meeting practices, project reporting practices, documentation needs and
escalation process.
D. Employee list with phone numbers and e-mail addresses, subcontractor list and customer
addresses.
Answer: C
Nokia Test Questions SDM_2002001050 exam prep SDM_2002001050 Free download SDM_2002001050 exam
10. What is the correct GIC to plan costs related to payment of a subcontractor responsible for
BTS commissioning?
A. 7331 Implementation.
B. 7332 Site Acquisition.
C. 7348 Project Management.
D. 7333 Construction Works.
Answer: A
Nokia Training online SDM_2002001050 Exam Dumps SDM_2002001050 Test Answers SDM_2002001050 Test Answers SDM_2002001050 Actual Test
11. What is NOT a risk response strategy?
A. Share.
B. Ignore.
C. Enhance.
D. Mitigate.
Answer: B
Nokia Latest Dumps SDM_2002001050 Latest Dumps SDM_2002001050 certification training SDM_2002001050 certification training
12. In today's project status meeting with the customer, the customer PM stated the following: "
The supplier of the transmission network has a huge delay, you can't start with your activities at the
moment".How does the PM react?
A. Make a re-planning of the project and immediately release the resources.
B. Start discussions about possible claims immediately in the meeting in order to have them on the
table already.
C. Initiate a meeting with the relevant stakeholders in NSN (CT, SSM's, project members) in order to
align the way forward and up sell strategy.
D. No reaction needed as the resources can be utilised for other projects.
Answer: C
Nokia dumps SDM_2002001050 Dumps PDF SDM_2002001050 SDM_2002001050 dumps
13. Which of the following is included in the scope statement?
A. Cost baseline.
B. Project quality plan.
C. Project plan.
D. Project deliverables.
Answer: D
Nokia SDM_2002001050 test questions SDM_2002001050 Exam Questions SDM_2002001050 Exam Prep SDM_2002001050 demo
14. In turnkey projects ...
A. ... Site acquisition and permitting very often turns out to become a critical bottleneck in the
projects. It is therefore highly recommended to plan very carefully for Site acquisition and
permitting and to develop a contingency plan.
B. ... Site acquisition and permitting as well as construction works are key competences in NSN.
Consequently these services should preferably NOT be outsourced to subcontractors.
C. ... if a base station site is connected via optical fiber transmission link to the network it is
important that a Line-of-Sight check is performed during site acquisition to ensure no obstacles
would interfere with the connection to the adjacent site.
D. ... revenue for Constructions Works services typically is comparatively small compared to revenue
for Site Acquisition&Permitting.
Answer: A
Nokia SDM_2002001050 SDM_2002001050 Dumps PDF SDM_2002001050 Exam Cost
15. When are sales usually recognized?
A. When goods receipt is posted in SAP .
B. When subcontractor invoice is received.
C. When the customer pays the invoice.
D. When the service is completed.
Answer: A
Nokia Test Answers SDM_2002001050 braindump SDM_2002001050 certification training SDM_2002001050 SDM_2002001050 questions SDM_2002001050 PDF VCE
NO.3 What are necessary inputs for the creation of a rollout plan?
A. Activity sequence, duration, resource requirements and schedule constraints.
B. List of deliverables, dependencies and estimated completion time.
C. Main milestones and activity duration.
D. Site process, activity sequencing and duration.
Answer: A
Nokia exam prep SDM_2002001050 exam SDM_2002001050 Practice Test
NO.4 Which KPI can assist the PM in the analysis of a Gross Margin deviation?
A. PARD
B. RA
C. PCA
D. SILT
Answer: C
Nokia questions SDM_2002001050 Dumps PDF SDM_2002001050 certification training
NO.5 Who is responsible to present the project results in the Project Review Meetings?
A. Project Manager with support of the CPM.
B. CPM and F&C.
C. CPM with support of the Project Manager.
D. Project Controller.
Answer: A
Nokia Braindumps SDM_2002001050 certification SDM_2002001050 SDM_2002001050 braindump SDM_2002001050
NO.6 The NI Performance Indicator SILT gives an understanding of...
A. ...the performance of Telecom Implementation Services.
B. ...the lead times of site infrastructure material.
C. ...the cash flow in the project.
D. ...the performed service quality.
Answer: C